Hop Long Bridge My Thuan 2 in mid-October

Hop Long Bridge My Thuan 2 in mid-October

My Thuan 2 Bridge is in the sprint construction phase, the investor and contractor are urgently completing the remaining items. Mid-October will meet the bridge, completing the project by the end of 2023.

Hop Long Bridge My Thuan 2 in mid-October - Photo 1.

On October 6, Mr. Trinh Truong Hai, Executive Director of the My Thuan 2 bridge project (Project Management Board 7), said that the My Thuan 2 bridge will be completed in mid-October. The project has a total length of more than 6 km, of which the main bridge is about 1.9 km long, designed with 6 lanes, speed of 80 km/h.

Hop Long Bridge My Thuan 2 in mid-October - Photo 2.

The project started construction in February 2020, with a total investment capital of about 5,000 billion VND. According to Project Management Board 7, up to now, the project has reached more than 93% of the contract value.

Hop Long Bridge My Thuan 2 in mid-October - Photo 3.

Of the five construction and installation packages, up to now, four have been basically completed. As for the main package of construction of the pier body from T14-T17, the structure on the main span of the cable-stayed span… is currently more than 85% completed.

Hop Long Bridge My Thuan 2 in mid-October - Photo 4.

With urgent progress, the contractor deployed three construction phases with dozens of workers fiercely constructing the remaining items.

Hop Long Bridge My Thuan 2 in mid-October - Photo 5.

Steel mold processing worker.

Hop Long Bridge My Thuan 2 in mid-October - Photo 6.

According to the design, the road leading to both ends of the bridge is more than 4 km long in Tien Giang and Vinh Long provinces. In the photo, workers are completing the final stages of completing the My Thuan 2 bridge.

Hop Long Bridge My Thuan 2 in mid-October - Photo 7.

Workers and engineers review technical elements on the tower.

Hop Long Bridge My Thuan 2 in mid-October - Photo 8.

“The current project progress is meeting the proposed plan. Workers are preparing the stages to complete the bridge, expected in mid-October. For some other items such as embankments to reinforce the current river bank, Construction is 50% completed,” Mr. Trinh Truong Hai added.

Source: bao Giaothong.vn